Oro Loma

Fresno County, California · EIA plant ID 59915 · Operator: RWE Clean Energy
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate20MWSummer 20 MW
Generators1in service
Net generation49GWh12 mo to Dec 2025
Capacity factor28%solar units, summer MW
Heat rate—thermal plants only
First online2017

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0246GWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2018202020222024202628.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20160——
201753.830.7%—
201852.730.1%—
201946.626.6%—
202051.229.1%—
202150.728.9%—
20225330.2%—
202325.314.5%—
202425.514.5%—
202549.228.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ORCASolar PhotovoltaicPV2020Jan 2017Operating—coming soon

Owner / operator

Operator: RWE Clean Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
RWE Clean Energy100.0%20 MW

Nearby plants

Within 80 km.
Althea Avenue Solar5 MW2 km
OWC Energy Holdings, LLC2 MW4.2 km
Zeta Solar & Storage—13.3 km
Merced 2 BESS2 MW13.8 km
Dos Palos Clean Power3 MW14.2 km
Vega Solar20 MW14.6 km