Imperial Valley Solar Co (IVSC) 2, LLC

Imperial County, California · EIA plant ID 59657 · Operator: Novatus Energy
SolarSolar PhotovoltaicBA: IID
Nameplate20MWSummer 20 MW
Generators1in service
Net generation44GWh12 mo to Dec 2025
Capacity factor25%solar units, summer MW
Heat rate—thermal plants only
First online2015

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
024GWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202625.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201518.618.1%—
201649.728.3%—
201748.327.6%—
201848.627.7%—
201947.427.0%—
20204425.0%—
202145.926.2%—
202245.225.8%—
202338.321.9%—
202446.226.3%—
202543.925.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
IVSC2Solar PhotovoltaicPV2020Jun 2015Operating—coming soon

Owner / operator

Operator: Novatus Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Novatus Energy100.0%20 MW

Nearby plants

Within 80 km.
Imperial Valley Solar Company 1 LLC23 MW0.7 km
Niland Gas Turbine Plant121 MW1.6 km
Wister Solar20 MW2 km
John L. Featherstone Plant55 MW8.8 km
Citizens Imperial Solar30 MW9 km
CE Turbo LLC12 MW9.6 km