← Back to map

Terra Francesco

San Bernardino County, California · EIA plant ID 59541 · Operator: Altus Power America Management, LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor17%solar units, summer MW
Heat rate—thermal plants only
First online2015

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202616.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20152.623.2%—
20163.123.7%—
2017323.2%—
20182.418.5%—
20192.821.7%—
20202.921.7%—
20212.217.0%—
20222.720.2%—
20231.611.8%—
20242.116.0%—
20252.216.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
3Solar PhotovoltaicPV1.51.5Mar 2015Operating—coming soon

Owner / operator

Operator: Altus Power America Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Altus Power America Management, LLC100.0%2 MW

Nearby plants

Within 80 km.
Kaiser Ontario1 MW0.8 km
KP Ontario Vineyard Solar2 MW0.9 km
Niagara Bottling Ontario PHI3 MW1.2 km
Oltmans SCE at Jurupa2 MW1.5 km
Solar Photovoltaic Project #06retired3.1 km
Solar Photovoltaic Project #32retired3.3 km