← Back to map

Town of Cary

Duplin County, North Carolina · EIA plant ID 59377 · Operator: Town Of Cary
SolarSolar PhotovoltaicBA: CPLE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor17%solar units, summer MW
Heat rate—thermal plants only
First online2012

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh201320142015201620172018201920202021202220242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%201420162018202020222024202617.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20132.417.9%—
20142.418.5%—
20152.317.2%—
20162.518.9%—
20172.418.4%—
20182.217.0%—
20192.418.1%—
20202.216.4%—
20212.216.9%—
20221.310.1%—
2024215.1%—
20252.317.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CARY1Solar PhotovoltaicPV1.51.5Dec 2012Operating—coming soon

Owner / operator

Operator: Town Of Cary. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Town Of Cary100.0%2 MW

Nearby plants

Within 80 km.
Rose Hill2 MW0 km
Buttercup Solar, LLC5 MW0.3 km
Hall Solar Energy Storage5 MW3.5 km
Hickory5 MW4.3 km
Aspen Solar, LLC5 MW5.3 km
Nickelson Solar, LLC5 MW8.7 km