Waste Mangement Redwood LFGTE
Marin County, California · EIA plant ID 59299 · Operator: WM Renewable Energy LLC
Nameplate4MWSummer 4 MW
Generators2in service
Net generation22GWh12 mo to Dec 2025
Capacity factor62%other units, summer MW
Heat rate—thermal plants only
First online2017
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2017 | 16.8 | 71.4% | — |
| 2018 | 28.5 | 81.4% | — |
| 2019 | 28.3 | 80.7% | — |
| 2020 | 25.5 | 72.7% | — |
| 2021 | 24.1 | 68.9% | — |
| 2022 | 20.5 | 58.4% | — |
| 2023 | 5.9 | 16.9% | — |
| 2024 | 13.1 | 37.3% | — |
| 2025 | 21.8 | 62.3% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| RED1 | Landfill Gas | IC | 2 | 2 | May 2017 | Operating | — | coming soon |
| RED2 | Landfill Gas | IC | 2 | 2 | May 2017 | Operating | — | coming soon |
Owner / operator
Operator: WM Renewable Energy LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| WM Renewable Energy LLC | 100.0% | 4 MW |
Nearby plants
Within 80 km.
| Silveira Ranch Road Solar | 3 MW | 0.8 km |
| Cottonwood Solar, LLC Cottonwood Carport | 1 MW | 3.5 km |
| Stage Gulch Solar | 1 MW | 6.5 km |
| Ellis Creek Solar | 4 MW | 6.9 km |
| Lavio Solar | 1 MW | 9.4 km |
| Bodega Avenue Solar LLC | 2 MW | 18.8 km |