← Back to map

Sterlington Greenworks LLC

Suffolk County, New York · EIA plant ID 59275 · Operator: AES Distributed Energy
SolarSolar PhotovoltaicNYISOBA: NYIS
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2015

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200MWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202624.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20150.39.2%—
20162.118.2%—
20172.219.2%—
20182.325.9%—
20192.225.5%—
2020222.3%—
20211.821.0%—
20221.820.1%—
20231.618.3%—
20242.224.6%—
20252.124.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
STERGSolar PhotovoltaicPV1.31Oct 2015Operating—coming soon

Owner / operator

Operator: AES Distributed Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
AES Distributed Energy100.0%1 MW

Nearby plants

Within 80 km.
Greenport10 MW6.9 km
Southold14 MW6.9 km
Hawkeye Energy Greenport LLC54 MW6.9 km
Kearsarge Southampton5 MW15.6 km
South Hampton12 MW19.3 km
East Hampton27 MW22.6 km