Goodnight
Armstrong County, Texas · EIA plant ID 59246 · Operator: FGE Goodnight I, LLC
Nameplate266MWSummer 266 MW
Generators1in service
Net generation797GWh12 mo to Aug 2026
Capacity factor34%wind units, summer MW
Heat rate—thermal plants only
First online2024
The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2024 | 575.2 | 32.8% | — |
| 2025 | 723.6 | 31.1% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GOOD1 | Onshore Wind Turbine | WT | 265.5 | 265.5 | Apr 2024 | Operating | — | vestas V136-4.2 |
Owner / operator
Operator: FGE Goodnight I, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| FGE Goodnight I, LLC | 100.0% | 266 MW |
Nearby plants
Within 80 km.
| Route 66 Wind Plant | 150 MW | 15.8 km |
| Grandview Wind Farm, LLC | 211 MW | 16.1 km |
| Goodnight Wind II | — | 20 km |
| Colbeck's Corner, LLC | 200 MW | 21.9 km |
| Project Matador Gas Plant (PMG) | — | 30.5 km |
| Project Matador Nuclear | — | 30.5 km |