← Back to map

Katama Farm

Dukes County, Massachusetts · EIA plant ID 59079 · Operator: Clean Focus Yield, LLC
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2014

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150200MWh20152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%201420162018202020222024202618.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20140.815.4%—
20151.618.1%—
20161.718.9%—
20170.910.3%—
20181.214.0%—
20191.516.6%—
20201.415.7%—
20211.416.3%—
20221.416.4%—
20231.618.3%—
20241.516.8%—
20251.618.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
KAT1Solar PhotovoltaicPV11Jun 2014Operating—coming soon

Owner / operator

Operator: Clean Focus Yield, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Clean Focus Yield, LLC100.0%1 MW

Nearby plants

Within 80 km.
Nunnepog1 MW1 km
West Tisbury Generating Facilityretired9.3 km
Oak Bluffs Diesel Generating Facilityretired10.5 km
Tisbury Landfill Solar1 MW12.3 km
Blacksmith Road Solar 17 MW27.7 km
Falmouth Landfill Solar3 MW28.5 km