← Back to map

ASTI

Sonoma County, California · EIA plant ID 58889 · Operator: Solar Star Arizona II LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate1MWSummer 1 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor12%solar units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150MWh2013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%201420162018202020222024202611.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20131.618.1%—
20141.416.6%—
20151.517.5%—
20161.517.5%—
20171.517.3%—
20181.416.2%—
20191.314.5%—
20201.416.2%—
20211.517.6%—
20221.413.6%—
20231.312.8%—
20241.211.0%—
20251.211.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ASTISolar PhotovoltaicPV1.21.2Feb 2009Operating—coming soon

Owner / operator

Operator: Solar Star Arizona II LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Solar Star Arizona II LLC100.0%1 MW

Nearby plants

Within 80 km.
Cloverdale Solar I2 MW3.9 km
Cloverdale Solar Center1 MW4 km
Warm Springs Hydro Project3 MW5.4 km
Aidlin Geothermal Power Plant25 MW11.5 km
Sonoma California Geothermal78 MW19.3 km
Bottle Rock Power55 MW19.8 km