← Back to map

Tulare 1 and 2

Tulare County, California · EIA plant ID 58642 · Operator: CD Arevon USA, Inc.
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate3MWSummer 3 MW
Generators2in service
Net generation5GWh12 mo to Dec 2025
Capacity factor21%solar units, summer MW
Heat rate—thermal plants only
First online2014

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600MWh201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%201420162018202020222024202620.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20145.621.2%—
20155.922.6%—
20165.922.3%—
20175.721.7%—
20185.320.3%—
20195.219.8%—
20204.717.7%—
20214.516.9%—
2022311.4%—
20230.62.4%—
20245.320.2%—
20255.420.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV1.51.5Jan 2014Operating—coming soon
2Solar PhotovoltaicPV1.51.5Jan 2014Operating—coming soon

Owner / operator

Operator: CD Arevon USA, Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
CD Arevon USA, Inc.100.0%3 MW

Nearby plants

Within 80 km.
Tulare BioMAT Fuel Cell3 MW4.3 km
City of Tulare Water Facility9 MW4.4 km
Central CA Fuel Cell 13 MW4.5 km
1875 West Street Solar2 MW5.2 km
TWC1 MW8.9 km
Lone Oak3 MW11.8 km