Los Angeles County, California · EIA plant ID 58451 · Operator: CD US Solar MT 2 LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor14%solar units, summer MW
Heat rate—thermal plants only
First online2013

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201420162018202020222024202613.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20130.823.4%—
2014430.8%—
20154.534.0%—
20164.333.0%—
20174.332.4%—
20184.333.1%—
20193.627.5%—
20203.627.3%—
20212.115.8%—
2022322.9%—
20234.231.7%—
20242.518.8%—
20251.813.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV1.51.5Oct 2013Operating—coming soon

Owner / operator

Operator: CD US Solar MT 2 LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
CD US Solar PO 2 LLC100.0%2 MW

Nearby plants

Within 80 km.
Lancaster Baptist Church1 MW0.3 km
Vinam2 MW2.9 km
Lancaster Solar 12 MW3.7 km
US-TOPCO (Soccer Center)3 MW4.2 km
Morgan Lancaster 12 MW4.3 km
Arrache 40062 MW4.6 km