← Back to map

East Campus Utility Plant

Hamilton County, Ohio · EIA plant ID 57929 · Operator: University of Cincinnati
OilPetroleum LiquidsPJMBA: PJM

×1 MW natural gas retired since 2020 (latest Mar 2024)

Nameplate6MWSummer 6 MW
Generators3in service
Net generation0GWh12 mo to Aug 2026
Capacity factor1%gas/coal/oil units, summer MW
Heat rate10,166Btu/kWhfossil units, electric fuel, HHV
First online2006Runs as rarely runs

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200MWh20112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%1%2%3%201220142016201820202022202420261.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
5,00010,00015,000201420162018202020222024202610,166 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20111.12.8%—
20120.10.3%—
20130.20.4%—
20140.10.2%10,526
20150.10.3%10,812
20160.10.4%7,493
20170.10.4%15,088
20180.30.7%10,067
20190.20.4%17,439
20200.10.1%10,878
20210.10.3%10,593
20220.20.4%10,997
20230.20.4%11,269
20240.10.3%10,286
20250.51.0%9,664

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
P007Petroleum LiquidsIC21.7Jul 2006Operating—coming soon
P008Petroleum LiquidsIC1.51.5Jul 2006Operating—coming soon
P058Petroleum LiquidsIC2.52.5May 2022Operating—coming soon
STGNatural Gas Steam TurbineST1.31.2Nov 2010Retired Mar 2024—coming soon

Owner / operator

Operator: University of Cincinnati. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
University of Cincinnati100.0%6 MW

Nearby plants

Within 80 km.
Central Utility Plant Cincinnati47 MW0.5 km
Parking Lot Array4 MW0.7 km
Procter & Gamble Cincinnati Plantretired4.1 km
RA Jones Roof Mounted Solar System1 MW12.4 km
Aero Solar Facility2 MW17.9 km
L'Oreal Solar - Florence1 MW18.9 km