Procter & Gamble Cincinnati PlantRetired

Hamilton County, Ohio · EIA plant ID 50456 · Operator: Procter & Gamble Co
Natural gasMISOBA: PJM

×13 MW natural gas retired since 2020 (latest Dec 2024)

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—Btu/kWhfossil units, electric fuel, HHV
First online—

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-20246GWh20022005200720092011201320152017201920212023

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%20052010201520202025

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
05,00010,00015,0002005201020152020
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200249.247.9%10,497
200440.439.3%5,070
200541.240.1%5,070
200644.343.2%5,070
200737.736.8%5,896
200846.144.9%4,869
200930.529.8%4,869
201046.445.3%4,869
20115351.7%4,869
201248.246.9%4,868
201339.538.5%4,935
20143332.2%4,868
201528.928.2%4,869
20162019.5%4,489
20172.52.4%—
20185.15.0%17,521
201912.912.6%8,807
202015.915.5%8,456
20217.57.3%14,920
20222.22.1%—
20239.49.2%4,675
202400.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Natural Gas Steam TurbineST12.511.7Nov 1965Retired Dec 2024—coming soon

Owner / operator

Operator: Procter & Gamble Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Parking Lot Array4 MW3.7 km
East Campus Utility Plant6 MW4.1 km
Central Utility Plant Cincinnati47 MW4.5 km
RA Jones Roof Mounted Solar System1 MW16.1 km
Willey Battery Utilityretired19.7 km
Hamilton Peaking32 MW19.8 km