Dartmouth Solar

Bristol County, Massachusetts · EIA plant ID 57473 · Operator: RWE Clean Energy
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor16%solar units, summer MW
Heat rate—thermal plants only
First online2011

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh201120122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2012201420162018202020222024202616.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201100.0%—
20122.215.9%—
20132.215.4%—
20142.316.4%—
20152.316.3%—
20162.417.1%—
20172.115.2%—
20182.115.2%—
20191.410.1%—
20202.316.6%—
20212.215.9%—
20222.215.5%—
20232.518.2%—
2024214.4%—
20252.316.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
DSMASolar PhotovoltaicPV1.61.6Mar 2011Operating—coming soon

Owner / operator

Operator: RWE Clean Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
RWE Clean Energy100.0%2 MW

Nearby plants

Within 80 km.
Acushnet Ball Plant 22 MW0.5 km
Greater New Bedford LFG Utiliz. Facility3 MW1.1 km
Acushnet- High Hill3 MW1.9 km
Bullock Road Solar 12 MW2 km
Acushnet-Braley Road 12 MW4 km
Braley Road 23 MW4 km