Martins Creek Solar NC, LLC

Cherokee County, North Carolina · EIA plant ID 57461 · Operator: Duke Energy Renewables Services
SolarSolar PhotovoltaicBA: DUK
Nameplate1MWSummer 1 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor16%solar units, summer MW
Heat rate—thermal plants only
First online2011

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150200MWh201120122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%2012201420162018202020222024202615.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20111.218.4%—
20121.417.7%—
20131.316.6%—
20141.417.3%—
20151.316.3%—
20161.417.7%—
20171.215.7%—
20181.114.5%—
20191.316.6%—
20201.214.6%—
20211.214.7%—
20221.215.7%—
20231.114.4%—
20241.114.0%—
20251.215.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV0.90.9Mar 2011Operating—coming soon

Owner / operator

Operator: Duke Energy Renewables Services. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Duke Energy Renewables Services100.0%1 MW

Nearby plants

Within 80 km.
Nottely16 MW9.5 km
Mission2 MW9.5 km
Murphy Farm Power, LLC1 MW13.1 km
CS Murphy Point, LLC1 MW14.1 km
Chatuge13 MW20.4 km