← Back to map

Pine Tree Solar Project

Kern County, California · EIA plant ID 57306 · Operator: Los Angeles Department of Water & Power
SolarSolar PhotovoltaicBA: LDWP
Nameplate9MWSummer 9 MW
Generators1in service
Net generation7GWh12 mo to Dec 2025
Capacity factor10%solar units, summer MW
Heat rate—thermal plants only
First online2013

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.5GWh201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%201420162018202020222024202610.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201313.621.7%—
201416.722.4%—
201510.313.9%—
201611.415.3%—
201714.719.8%—
201814.719.7%—
201912.717.1%—
202010.113.5%—
20218.311.2%—
202212.717.1%—
20236.99.2%—
20247.29.6%—
20257.410.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV8.58.5Mar 2013Operating—coming soon

Owner / operator

Operator: Los Angeles Department of Water & Power. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Los Angeles Department of Water & Power100.0%9 MW

Nearby plants

Within 80 km.
Pine Tree Wind Power Project135 MW2.8 km
Sky River Wind Energy Center60 MW5.8 km
RE Barren Ridge 160 MW11.9 km
North Sky River Energy LLC162 MW13.2 km
Beacon Solar Plant Site 538 MW14.8 km
Hecate Energy Beacon Solar 450 MW15.6 km