PPL Frey Farm Landfill Wind

Lancaster County, Pennsylvania · EIA plant ID 57182 · Operator: EPP Renewable Energy
WindOnshore Wind TurbinePJMBA: PJM
Nameplate3MWSummer 3 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor3%wind units, summer MW
Heat rate—thermal plants only
First online2011

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800MWh201120122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%201220142016201820202022202420263.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20116.121.9%—
20126.222.0%—
20136.523.1%—
20146.322.5%—
20156.121.9%—
20166.723.7%—
20176.222.1%—
20186.222.0%—
2019621.6%—
20206.422.9%—
20215.720.2%—
20225.920.9%—
20235.620.1%—
20243.412.2%—
20250.93.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT3.23.2Jan 2011Operating—ge 1.6 XLE

Owner / operator

Operator: EPP Renewable Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
EPP Renewable Energy100.0%3 MW

Nearby plants

Within 80 km.
Frey Farm Landfill3 MW1 km
Safe Harbor418 MW6.8 km
Mount Joy Wire1 MW16.7 km
PPL Holtwood247 MW18.1 km
York Generation Company LLCretired19 km