← Back to map

Merricourt Wind Energy Center

McIntosh County, North Dakota · EIA plant ID 57048 · Operator: Otter Tail Power Co
WindOnshore Wind TurbineMISOBA: MISO
Nameplate150MWSummer 150 MW
Generators1in service
Net generation561GWh12 mo to Aug 2026
Capacity factor43%wind units, summer MW
Heat rate—thermal plants only
First online2020

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0204060GWh202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2020202120222023202420252026202742.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20203329.5%—
2021501.638.2%—
2022575.743.8%—
2023594.745.3%—
2024573.543.5%—
2025583.544.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT150150Dec 2020Operating—vestas V110-2.0

Owner / operator

Operator: Otter Tail Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Otter Tail Power Co100.0%150 MW

Nearby plants

Within 80 km.
Foxtail Wind, LLC150 MW13.8 km
Tatanka Wind Power LLC180 MW18.6 km
FPL Energy North Dakota Wind I/II62 MW27.4 km
Badger Wind, LLC250 MW43.3 km
Emmons-Logan Energy Storage—76.6 km