Walgreens Woodland Distribution Center
Yolo County, California · EIA plant ID 57006 · Operator: SunE WG45 Woodland LLC
Nameplate1MWSummer 1 MW
Generators1in service
Net generation0GWh12 mo to Dec 2025
Capacity factor5%solar units, summer MW
Heat rate—thermal plants only
First online2007
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2009 | 1.8 | 22.8% | — |
| 2010 | 1.7 | 21.3% | — |
| 2011 | 1.7 | 22.0% | — |
| 2012 | 1.7 | 20.9% | — |
| 2013 | 1.5 | 19.6% | — |
| 2014 | 1.6 | 20.1% | — |
| 2015 | 1.5 | 18.6% | — |
| 2016 | 0.5 | 5.8% | — |
| 2017 | 0.7 | 8.4% | — |
| 2018 | 0.8 | 10.5% | — |
| 2019 | 1.6 | 19.9% | — |
| 2020 | 1.3 | 17.0% | — |
| 2021 | 1.2 | 15.1% | — |
| 2022 | 1 | 12.8% | — |
| 2023 | 0.8 | 9.8% | — |
| 2024 | 0.9 | 11.5% | — |
| 2025 | 0.4 | 5.5% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| 1 | Solar Photovoltaic | PV | 1 | 0.9 | Aug 2007 | Operating | — | coming soon |
Owner / operator
Operator: SunE WG45 Woodland LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| SunE WG45 Woodland LLC | 100.0% | 1 MW |
Nearby plants
Within 80 km.
| Target Woodland Solar Project | 2 MW | 1.2 km |
| Yolo County Solar Project | 1 MW | 2.2 km |
| Woodland Biomass Power Ltd | 28 MW | 2.7 km |
| MM Yolo Power | 4 MW | 9 km |
| SCDA Solar 1 | 7 MW | 11.1 km |
| Chambers 4 - Sacramento SMF1 | 3 MW | 12.1 km |