Lamar Power Project

Lamar County, Texas · EIA plant ID 55097 · Operator: LaFrontera Holdings LLC
Natural gasNatural Gas Fired Combined CycleERCOTBA: ERCO
Nameplate1,113MWSummer 1,044 MW
Generators6in service
Net generation7,354GWh12 mo to Aug 2026
Capacity factor80%gas/coal/oil units, summer MW
Heat rate7,040Btu/kWhfossil units, electric fuel, HHV
First online2000Runs as baseload

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202580.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
6,0007,0008,000200520102015202020257,040 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20014,992——
20025,685.8——
20033,435.836.0%8,702
20043,632.841.2%7,310
20053,789.343.1%7,851
20064,508.451.3%7,251
20074,373.249.7%7,848
20083,665.641.6%7,497
20095,188.159.0%7,238
20103,331.737.9%8,112
20114,295.548.8%7,657
20124,913.255.8%7,599
20135,193.959.2%7,274
20145,333.860.8%7,446
20155,999.168.3%7,405
20166,053.967.7%7,175
20176,150.366.7%7,184
20187,285.180.3%7,113
20197,004.377.2%7,154
20207,022.177.2%7,123
20216,130.669.7%7,060
20225,477.762.3%7,163
20235,659.364.3%7,113
20245,938.367.3%7,032
20256,862.875.0%7,015

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CTG1Natural Gas Fired Combined CycleCT176158May 2000Operating—coming soon
CTG2Natural Gas Fired Combined CycleCT176150May 2000Operating—coming soon
CTG3Natural Gas Fired Combined CycleCT176160Dec 2000Operating—coming soon
CTG4Natural Gas Fired Combined CycleCT176168Dec 2000Operating—coming soon
STG1Natural Gas Fired Combined CycleCA204.3204May 2000Operating—coming soon
STG2Natural Gas Fired Combined CycleCA204.3204May 2000Operating—coming soon

Owner / operator

Operator: LaFrontera Holdings LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
LaFrontera Holdings LLC100.0%1,113 MW

Nearby plants

Within 80 km.
MRG Goody Solar Project Hybrid—3.7 km
Tyson Nick91 MW3.8 km
Eiffel Solar Project240 MW7 km
Paris Energy Center266 MW7.9 km
Roscommon Solar Park—9.8 km
Echols Grove Solar—12.3 km