← Back to map

Rock Creek LP

El Dorado County, California · EIA plant ID 50892 · Operator: Hydroland Omega LLC
HydroConventional HydroelectricCAISOBA: CISO
Nameplate3MWSummer 3 MW
Generators2in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online1986

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800MWh20022004200620082010201220142016201820202022

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2005201020152020

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20022.17.9%—
200327.6%—
200400.0%—
200500.0%—
2006726.6%—
20070.93.5%—
20080.62.4%—
20091.34.9%—
20103.914.6%—
20115.922.4%—
20122.610.0%—
20130.20.8%—
20140.62.3%—
20150.10.4%—
20161.34.9%—
20172.49.1%—
20181.55.6%—
20191.76.5%—
20200.62.1%—
20210.10.3%—
20220.62.3%—
20230.62.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Conventional HydroelectricHY1.51.5Apr 1986Operating—coming soon
GEN2Conventional HydroelectricHY1.51.5Apr 1986Operating—coming soon

Owner / operator

Operator: Hydroland Omega LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Hydroland Omega LLC100.0%3 MW

Nearby plants

Within 80 km.
White Rock/Slab Creek269 MW2.2 km
Chili Bar8 MW3.3 km
El Dorado County2 MW10.4 km
El Dorado20 MW13.9 km
Camino158 MW21.5 km
Jaybird162 MW22.1 km