Kent County Waste to Energy Facility

Kent County, Michigan · EIA plant ID 50860 · Operator: Kent County
OtherMunicipal Solid WasteMISOBA: MISO
Nameplate18MWSummer 16 MW
Generators1in service
Net generation78GWh12 mo to Aug 2026
Capacity factor56%other units, summer MW
Heat rate22,946Btu/kWhfossil units, electric fuel, HHV
First online1989

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02.557.510GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202556.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
18,00020,00022,00024,0002005201020152020202522,946 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001102.574.6%—
2002102.374.4%—
200386.262.7%—
2004105.175.3%19,450
2005100.572.4%20,439
2006108.278.4%19,104
200798.571.6%—
2008101.973.9%—
200999.772.5%—
2010104.876.2%—
2011101.673.9%—
201296.570.0%—
2013104.775.6%20,223
2014100.572.5%19,927
201510072.1%19,601
2016100.872.5%20,148
201799.571.9%19,437
2018102.374.0%20,221
20199669.5%24,069
2020100.872.6%20,639
2021101.473.5%20,740
202296.669.8%21,348
202393.467.9%21,964
202498.471.1%21,001
202599.572.1%20,471

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Municipal Solid WasteST1815.7Oct 1989Operating—coming soon

Owner / operator

Operator: Kent County. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Kent County100.0%18 MW

Nearby plants

Within 80 km.
Bissell Solar and Battery Generator1 MW6.9 km
Ada Cogeneration LP33 MW16.3 km
Cascade Dam2 MW16.4 km
Ada Dam1 MW16.9 km
Grand Valley Solar Gardens3 MW16.9 km
Bryon Center5 MW18.8 km