← Back to map

Mio

Oscoda County, Michigan · EIA plant ID 1714 · Operator: Consumers Energy Co
HydroConventional HydroelectricMISOBA: MISO
Nameplate5MWSummer 1 MW
Generators2in service
Net generation14GWh12 mo to Dec 2025
Capacity factor111%!hydro units, summer MW
Heat rate—thermal plants only
First online1916

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-10123GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%20052010201520202025110.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200112.991.9%—
200212.891.0%—
200311.582.1%—
200414.1100.4%—
200513.395.1%—
200615.4109.6%—
200713.797.5%—
200815.2108.4%—
200914.2101.6%—
20109.568.0%—
201113.8112.4%—
201213105.5%—
201314.840.3%—
201416.344.4%—
201515.642.4%—
201616.4133.3%—
201716.7135.9%—
201815.6111.2%—
201918.5131.8%—
202018.2137.9%—
202115107.0%—
202214.1100.9%—
20231081.2%—
202413.6110.7%—
202513.6110.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY2.50.7Jan 1916Operating—coming soon
2Conventional HydroelectricHY2.50.7Jan 1916Operating—coming soon

Owner / operator

Operator: Consumers Energy Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Consumers Energy Co100.0%5 MW

Nearby plants

Within 80 km.
Lightfoot Solar, LLC10 MW4.2 km
Alcona8 MW28.1 km
Loud4 MW39.3 km
Five Channels6 MW42.7 km
Grayling Generating Station39 MW44.7 km
Cooke9 MW49 km