← Back to map

Loud

Iosco County, Michigan · EIA plant ID 1712 · Operator: Consumers Energy Co
HydroConventional HydroelectricMISOBA: MISO
Nameplate4MWSummer 5 MW
Generators2in service
Net generation16GWh12 mo to Dec 2025
Capacity factor37%hydro units, summer MW
Heat rate—thermal plants only
First online1913

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
01234GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%2005201020152020202537.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200115.841.1%—
200215.941.4%—
200314.838.3%—
200417.445.0%—
200516.442.6%—
200618.949.0%—
200717.244.5%—
200818.948.9%—
200918.748.6%—
20101641.6%—
201117.244.6%—
201216.237.6%—
201317.645.7%—
201417.846.1%—
201517.842.4%—
201619.9119.0%—
201720.653.4%—
201819.342.4%—
201921.146.4%—
202019.951.6%—
202113.234.1%—
202218.143.0%—
202316.738.2%—
202416.738.8%—
202516.137.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY22.5Jan 1913Operating—coming soon
2Conventional HydroelectricHY22.4Jan 1913Operating—coming soon

Owner / operator

Operator: Consumers Energy Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Consumers Energy Co100.0%4 MW

Nearby plants

Within 80 km.
Five Channels6 MW3.6 km
Cooke9 MW11.9 km
Alcona8 MW12.8 km
Foote9 MW22.4 km
Viking Energy of Lincoln20 MW34.1 km
Au Gres Solar Park—38.8 km