← Back to map

Clement Dam Hydro LLC

Belknap County, New Hampshire · EIA plant ID 10276 · Operator: Eagle Creek RE LLC
HydroConventional HydroelectricISONEBA: ISNE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation6GWh12 mo to Dec 2025
Capacity factor32%hydro units, summer MW
Heat rate—thermal plants only
First online1984

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
012GWh200120032005200720092011201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%100%200%300%2005201020152020202532.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20018.635.3%—
20025.321.7%—
200311.340.6%—
20049.836.1%—
200513.292.7%—
200612.8111.1%—
20075.4310.6%—
200814.5117.6%—
200913.898.2%—
20108.9145.3%—
201112.6110.7%—
201200.0%—
201416.179.9%—
20158.542.1%—
20164.421.6%—
201710.451.6%—
201810.552.3%—
201910.753.2%—
20207.637.4%—
20218.843.6%—
20228.140.1%—
202311.958.9%—
20248.943.9%—
20256.432.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
49Conventional HydroelectricHY2.42.3Dec 1984Operating—coming soon

Owner / operator

Operator: Eagle Creek RE LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Clement Dam Hydroelectric, LLC100.0%2 MW

Nearby plants

Within 80 km.
Stevens Mills Dam2 MW4 km
Eastman Falls6 MW5.1 km
Lochmere Hydroelectric Plant1 MW6.2 km
Wheelabrator Concord Facility14 MW17.2 km
Penacook Lower Falls5 MW17.2 km
Penacook Upper Falls Hydro3 MW17.5 km