← Back to map

Arvada

Sheridan County, Wyoming · EIA plant ID 8028 · Operator: Basin Electric Power Coop
Natural gasNatural Gas Fired Combustion TurbineBA: WACM

×8 MW natural gas retired since 2020 (latest Dec 2021)

Nameplate15MWSummer 10 MW
Generators2in service
Net generation0GWh12 mo to Dec 2025
Capacity factor0%gas/coal/oil units, summer MW
Heat rate18,304Btu/kWhfossil units, electric fuel, HHV
First online2002Runs as rarely runs

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0246GWh200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%200520102015202020250.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
10,00015,00020,0002005201020152020202518,304 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200213.325.3%12,187
20037.14.5%12,603
20045.43.8%11,726
20050.90.7%12,779
20061.91.4%13,104
200723.517.9%12,591
20085.74.3%13,029
20094.63.5%12,647
20102.31.8%13,061
20111.10.8%13,809
20120.30.3%16,360
20130.30.3%14,020
20140.40.3%19,646
20150.20.1%14,530
20160.20.1%14,503
20170.20.1%14,853
20180.20.2%16,671
20190.20.1%20,545
20200.60.5%17,947
20210.90.7%16,114
20220.30.4%16,727
20230.20.3%17,560
20240.20.2%17,261
20250.20.2%18,304

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Natural Gas Fired Combustion TurbineGT7.55Sep 2002Operating—coming soon
2Natural Gas Fired Combustion TurbineGT7.55Sep 2002Operating—coming soon
3Natural Gas Fired Combustion TurbineGT7.55Sep 2002Retired Dec 2021—coming soon

Owner / operator

Operator: Basin Electric Power Coop. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Basin Electric Power Coop100.0%15 MW

Nearby plants

Within 80 km.
Dry Fork Station484 MW61.3 km
Wygen 295 MW72.8 km
Wygen III116 MW72.8 km
Wyodak362 MW72.9 km
Wygen 190 MW73 km
Neil Simpson II130 MW73.1 km