← Back to map

Pinopolis BESSPlanned

Berkeley County, South Carolina · EIA plant ID 70020 · Operator: Pinopolis BESS LLC
BatteryBA: SC

300 MW planned (Batteries), first expected Sep 2027 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1BatteriesBA300300planned Sep 2027Planned—coming soon

Owner / operator

Operator: Pinopolis BESS LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Jefferies145 MW0.6 km
Berkeley County Landfill3 MW14.6 km
Cross2,452 MW18.3 km
St Stephen84 MW20.6 km
Williams660 MW26.2 km
Bushy Park Combustion Turbine Facility65 MW26.3 km