Charger SolarUnder construction

Refugio County, Texas · EIA plant ID 69877 · Operator: AP Solar 4 LLC
SolarERCOTBA: ERCO

394 MW under construction (Solar Photovoltaic), first expected Oct 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 394 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CHPV1Solar PhotovoltaicPV394.4394.4planned Oct 2026Under construction—coming soon

Owner / operator

Operator: AP Solar 4 LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Seadrift Coke LP8 MW25.9 km
BP Chemicals Green Lake Plant39 MW26.1 km
Union Carbide Seadrift Cogen168 MW27.9 km
Victoria Texas Plant102 MW29.8 km
Victoria Port Power II LLC100 MW32.5 km
Victoria Port Power LLC100 MW32.7 km