← Back to map

Lion SolarPlanned

Jefferson County, Arkansas · EIA plant ID 69633 · Operator: Lion Solar LLC
SolarMISOBA: MISO

200 MW planned (Solar Photovoltaic), first expected Dec 2029 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
99757Solar PhotovoltaicPV200200planned Dec 2029Planned—coming soon

Owner / operator

Operator: Lion Solar LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
SR Altheimer—7.3 km
Pine Bluff Mill85 MW11.6 km
Pine Bluff Energy Center230 MW12 km
Arkansas Cypress Solar Station—17.7 km
Colonel Charles D. Maynard Project—19 km
White Bluff1,800 MW22.6 km