NL MA - Division
Bristol County, Massachusetts · EIA plant ID 69568 · Operator: Standard Solar
Nameplate2MWSummer 2 MW
Generators2in service
Net generation0GWh12 mo to Dec 2025
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2025
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2025 | 0 | — | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| DIVIB | Batteries | BA | 1 | 1 | Sep 2025 | Operating | — | coming soon |
| DIVIS | Solar Photovoltaic | PV | 1 | 1 | Sep 2025 | Operating | — | coming soon |
Owner / operator
Operator: Standard Solar. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Standard Solar | 100.0% | 2 MW |
Nearby plants
Within 80 km.
| Dartmouth Landfill | 1 MW | 3.4 km |
| Fisher Road Solar | 5 MW | 3.6 km |
| Westport (MA) | 3 MW | 4.4 km |
| Pine Hill Westport | 3 MW | 4.8 km |
| Brookwood Drive Community Solar | 8 MW | 6.1 km |
| Westport Stone & Sand Solar (CSG) | 5 MW | 6.8 km |