← Back to map

Rockfish Solar

Cumberland County, North Carolina · EIA plant ID 69565 · Operator: Public Works Comm-City of Fayetteville
SolarSolar PhotovoltaicBA: CPLE
Nameplate5MWSummer 5 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor12%solar units, summer MW
Heat rate—thermal plants only
First online2025

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600MWh2025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%2025202611.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20251.311.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV4.94.9Oct 2025Operating—coming soon

Owner / operator

Operator: Public Works Comm-City of Fayetteville. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Public Works Comm-City of Fayetteville100.0%5 MW

Nearby plants

Within 80 km.
Gillespie Street Solar2 MW6.8 km
Carter PV15 MW8 km
Panda Solar NC 9, LLC2 MW8.9 km
Panda Solar NC 10, LLC2 MW9 km
Panda Solar NC 11, LLC2 MW9 km
Butler10 MW9 km