← Back to map

Wheeler Gulch Solar, LLC

Garfield County, Colorado · EIA plant ID 69287 · Operator: Standard Solar
SolarSolar PhotovoltaicBA: PSCO
Nameplate10MWSummer 10 MW
Generators1in service
Net generation17GWh12 mo to Dec 2025
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2023

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0123GWh2025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2025202620.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202517.520.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
HUSONSolar PhotovoltaicPV9.99.9Dec 2023Operating—coming soon

Owner / operator

Operator: Standard Solar. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Standard Solar100.0%10 MW

Nearby plants

Within 80 km.
Pivot Solar 3 LLC (CSG)2 MW7.6 km
High Mesa CO22 MW9.9 km
Pivot Solar 7 LLC (CSG)2 MW24.9 km
Oak Leaf Solar XXXII (CSG)2 MW24.9 km
WWRF Solar Plant2 MW25 km
Rifle Generating Stationretired32 km