← Back to map

Blairs Valley Solar Project

Franklin County, Pennsylvania · EIA plant ID 69235 · Operator: CleanChoice Energy
SolarSolar PhotovoltaicPJMBA: PJM
Nameplate20MWSummer 20 MW
Generators1in service
Net generation10GWh12 mo to Dec 2025
Capacity factor12%solar units, summer MW
Heat rate—thermal plants only
First online2025

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.52GWh2025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%2025202611.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202510.311.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BVCCESolar PhotovoltaicPV2020Jul 2025Operating—coming soon

Owner / operator

Operator: CleanChoice Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
CCE Genco, LLC51.0%10 MW
Churchill Stateside Renewable Energy Fund XXXIV, LLC?49.0%10 MW

Nearby plants

Within 80 km.
Elk Hill Solar 120 MW5.1 km
Elk Hill Solar 215 MW9.4 km
Mountain View14 MW11.4 km
Great Cove Solar II150 MW11.8 km
Whitetail Solar 220 MW14.5 km
Whitetail Solar 320 MW15.4 km