Arroyo SolarUnder construction

Pueblo County, Colorado · EIA plant ID 69040 · Operator: Public Service Co of Colorado
SolarBA: PSCO

335 MW under construction (Solar Photovoltaic), first expected Oct 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 335 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ARY1Solar PhotovoltaicPV335335planned Oct 2026Under construction—coming soon

Owner / operator

Operator: Public Service Co of Colorado. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Rocky Mountain Solar525 MW2.6 km
Sun Mountain Solar 1200 MW3.4 km
Stagecoach LRE—4.5 km
Comanche Solar120 MW5.1 km
Comanche (CO)1,253 MW5.6 km