Bayer Oxnard - Meter# 4719
Ventura County, California · EIA plant ID 68540 · Operator: Camino del Sol 2 Solar Project 2022, LLC
Nameplate1MWSummer 1 MW
Generators1in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online2026
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| 6245 | Solar Photovoltaic | PV | 1.3 | 1.3 | Mar 2026 | Operating | — | coming soon |
Owner / operator
Operator: Camino del Sol 2 Solar Project 2022, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Camino del Sol 2 Solar Project 2022, LLC | 100.0% | 1 MW |
Nearby plants
Within 80 km.
| SunEdison Procter & Gamble Oxnard | 1 MW | 1.1 km |
| CA OXNARD 2600 Sakioka Dr | 3 MW | 1.1 km |
| IGS OXR1 | 5 MW | 1.4 km |
| E F Oxnard Energy Facility | 49 MW | 2.6 km |
| Oxnard | 69 MW | 2.6 km |
| CA-Ventura Co CCD-Oxnard College Canopy | 2 MW | 4.5 km |