← Back to map

SR South BastropUnder construction

Morehouse County, Louisiana · EIA plant ID 68256 · Operator: SR South Bastrop, LLC
SolarMISOBA: MISO

5 MW under construction (Solar Photovoltaic), first expected Dec 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 5 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SBASTSolar PhotovoltaicPV4.84.8planned Dec 2026Under construction—coming soon

Owner / operator

Operator: SR South Bastrop, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
SR North Bastrop—6.2 km
Perryville Power Station824 MW11.9 km
Bayou Galion Solar Project98 MW13.1 km
Ouachita904 MW15.4 km
Sterlington Solar49 MW15.8 km
Sterlington59 MW16.4 km