Findley PV and BESSPlanned
Limestone County, Texas · EIA plant ID 67778 · Operator: Gransolar Texas Sixteen, LLC
101 MW planned (Batteries, Solar Photovoltaic), first expected Jan 2028 · EIA-860M
Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GR16B | Batteries | BA | 50.3 | 50.3 | planned Jan 2028 | Planned | — | coming soon |
| GR16P | Solar Photovoltaic | PV | 50.3 | 50.3 | planned Jan 2028 | Planned | — | coming soon |
Owner / operator
Operator: Gransolar Texas Sixteen, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Waco Solar II | — | 7.6 km |
| Waco Solar | 400 MW | 8.3 km |
| Hubbard Wind | 300 MW | 15.3 km |
| Prairie Hill Wind Project | 300 MW | 15.7 km |
| Naduah Solar | — | 16.9 km |
| PP Jaguar BESS LLC | 300 MW | 18.7 km |