Stampede Solar Hybrid

Hopkins County, Texas · EIA plant ID 67762 · Operator: Stampede Solar Project LLC
SolarBatteriesSolar PhotovoltaicERCOTBA: ERCO
Nameplate328MWSummer 328 MW
Generators2in service
Net generation534GWh12 mo to Aug 2026
Capacity factor29%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0204060GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%150%20252026202728.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2024113.5——
2025540.8146.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
STMPBBatteriesBA72.272.2Oct 2024Operating—coming soon
STMPSSolar PhotovoltaicPV255.9255.9Nov 2025Operating—coming soon

Owner / operator

Operator: Stampede Solar Project LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Stampede Solar Project LLC100.0%328 MW

Nearby plants

Within 80 km.
Samson Solar Energy250 MW12.9 km
Pine Forest Solar I500 MW13.1 km
Hopkins Energy LLC250 MW13.4 km
Delilah Solar Energy LLC300 MW17.2 km
Talco Solar Project8 MW21.5 km
Mockingbird Solar Center471 MW23.3 km