SolarBatteriesSolar PhotovoltaicBA: AZPS
Nameplate600MWSummer 600 MW
Generators2in service
Net generation827GWh12 mo to Aug 2026
Capacity factor33%solar units, summer MW
Heat rate—thermal plants only
First online2025

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
020406080GWh2026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20252026202733.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2025648.334.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BESS1BatteriesBA300300Apr 2025Operating—coming soon
PV1Solar PhotovoltaicPV300300Apr 2025Operating—coming soon

Owner / operator

Operator: Copia Power. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Copia Power100.0%600 MW

Nearby plants

Within 80 km.
Maricopa Solar550 MW0.3 km
Harquahala Generating Project1,277 MW1.8 km
Harquahala Sun Solar Project150 MW3.2 km
Desert Sand BESS—6.8 km
Papago PV150 MW6.9 km
Papago Energy Storage300 MW7.2 km