← Back to map

Cedar Springs Wind IV

Converse County, Wyoming · EIA plant ID 67289 · Operator: Cedar Springs Wind IV, LLC
WindOnshore Wind TurbineBA: WACM
Nameplate390MWSummer 390 MW
Generators1in service
Net generation1,313GWh12 mo to Aug 2026
Capacity factor38%wind units, summer MW
Heat rate—thermal plants only
First online2025

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20252026202738.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20251,055.630.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CS4Onshore Wind TurbineWT390.4390.4Jan 2025Operating—ge 5.5-158

Owner / operator

Operator: Cedar Springs Wind IV, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Cedar Springs Wind IV, LLC100.0%390 MW

Nearby plants

Within 80 km.
Cedar Springs III133 MW10.7 km
Rolling Hills116 MW12.6 km
Glenrock166 MW13.6 km
Top of the World Windpower Project200 MW20.4 km
Cedar Springs I200 MW21.4 km
Campbell Hill Windpower99 MW25.2 km