WindOnshore Wind TurbineBA: WACM
Nameplate106MWSummer 106 MW
Generators1in service
Net generation406GWh12 mo to Aug 2026
Capacity factor44%wind units, summer MW
Heat rate—thermal plants only
First online2023

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2023202420252026202743.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202300.0%—
2024393.642.4%—
2025376.440.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
RHIIOnshore Wind TurbineWT105.7105.7Dec 2023Operating—ge 2.82-127

Owner / operator

Operator: Roundhouse Renewable Energy II, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Roundhouse Renewable Energy II, LLC100.0%106 MW

Nearby plants

Within 80 km.
Corriedale Wind Energy53 MW6.6 km
Silver Sage Windpower42 MW8.7 km
Happy Jack Windpower Project29 MW9.5 km
Roundhouse Wind Energy Project226 MW10.4 km
South Cheyenne Solar150 MW18.7 km
Bison Solar LLC30 MW21.3 km