← Back to map

Umbriel Solar

Polk County, Texas · EIA plant ID 66954 · Operator: Umbriel Solar, LLC
SolarSolar PhotovoltaicMISOBA: MISO
Nameplate150MWSummer 150 MW
Generators1in service
Net generation325GWh12 mo to Aug 2026
Capacity factor25%solar units, summer MW
Heat rate—thermal plants only
First online2023

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2023202420252026202724.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202365.219.7%—
2024323.424.6%—
2025318.924.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
23001Solar PhotovoltaicPV150150Oct 2023Operating—coming soon

Owner / operator

Operator: Umbriel Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Umbriel Solar, LLC100.0%150 MW

Nearby plants

Within 80 km.
Segno Solar Station—13.8 km
RC Thomas Hydroelectric Project27 MW22 km
Votaw Solar Station—28 km
Longwing Solar—34.1 km
Woodville Renewable Power Project50 MW34.2 km
San Jacinto County Peaking Facility170 MW35.3 km