Kaufman County, Texas · EIA plant ID 66905 · Operator: Ables Springs Solar, LLC
BatteryBatteriesERCOTBA: ERCO

151 MW under construction (Solar Photovoltaic), first expected Oct 2026 · EIA-860M

Nameplate100MWSummer 100 MW
Generators1in service · 151 MW building
Net generation306GWh12 mo to Aug 2026
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2025

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2025309.8——

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BESSBatteriesBA100100Jun 2025Operating—coming soon
SOLARSolar PhotovoltaicPV151151planned Oct 2026Under construction—coming soon

Owner / operator

Operator: Ables Springs Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Ables Springs Storage, LLC100.0%100 MW

Nearby plants

Within 80 km.
Mystic Springs Renewable Energy (Hybrid)—0.6 km
BT Signal Ranch50 MW20.7 km
TE Smith Storage125 MW22.7 km
Cunningham Storage190 MW22.9 km
Wigeon Whistle Battery Storage Plant120 MW28.4 km
Forney Energy Center1,894 MW29.5 km