Jones City 2 SolarUnder construction
Jones County, Texas · EIA plant ID 66893 · Operator: Lightsource Renewable Energy Asset Management, LLC
385 MW under construction (Batteries, Solar Photovoltaic), first expected Oct 2026 · EIA-860M
Nameplate—MWSummer — MW
Generators0in service · 385 MW building
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| TXJC2 | Solar Photovoltaic | PV | 185 | 185 | planned Oct 2026 | Under construction | — | coming soon |
| TXJS2 | Batteries | BA | 200 | 200 | planned Mar 2027 | Under construction | — | coming soon |
Owner / operator
Operator: Lightsource Renewable Energy Asset Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Jones City 1 Solar | — | 2 km |
| Anson 2 Solar | — | 7 km |
| ANSON Solar Center, LLC | 200 MW | 7.3 km |
| Tiger Solar | — | 10.5 km |
| Swenson Solar | — | 21.4 km |
| Funston Solar | — | 25.5 km |