← Back to map

Cicero Energy Storage 1 LLC

Onondaga County, New York · EIA plant ID 66501 · Operator: Convergent Energy and Power LP
SolarBatteriesSolar PhotovoltaicNYISOBA: NYIS
Nameplate10MWSummer 10 MW
Generators2in service
Net generation7GWh12 mo to Dec 2025
Capacity factor16%solar units, summer MW
Heat rate—thermal plants only
First online2022

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-0.500.51GWh202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%2022202320242025202615.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20224.111.1%—
20237.417.0%—
2024715.8%—
20256.915.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CCBA1BatteriesBA55Mar 2022Operating—coming soon
CCPV1Solar PhotovoltaicPV55Mar 2022Operating—coming soon

Owner / operator

Operator: Convergent Energy and Power LP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Convergent Energy and Power LP100.0%10 MW

Nearby plants

Within 80 km.
Cicero Energy Storage 2 LLC10 MW0.5 km
Onondaga County - Oak Orchard WWTP2 MW4.5 km
Source Power II - Taft CSG4 MW4.6 km
Summit - Cicero5 MW6.4 km
Bartell South PV I—7.4 km
Ver Plank South (CSG)5 MW8.9 km