← Back to map

Town of Amherst Solar

Hampshire County, Massachusetts · EIA plant ID 66182 · Operator: Agilitas Energy, LLC
SolarBatteriesSolar PhotovoltaicISONEBA: ISNE
Nameplate5MWSummer 5 MW
Generators2in service
Net generation4GWh12 mo to Dec 2025
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2022

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2022202320242025202620.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20221.111.9%—
20234.118.8%—
2024419.5%—
20254.520.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
AMHBABatteriesBA2.52.5Aug 2022Operating—coming soon
AMHPVSolar PhotovoltaicPV2.52.5Aug 2022Operating—coming soon

Owner / operator

Operator: Agilitas Energy, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Agilitas Energy, LLC100.0%5 MW

Nearby plants

Within 80 km.
Hampshire College Hybrid4 MW2.5 km
Amherst College Co Gen1 MW3.2 km
Hadley Solar NG, LLC3 MW4.9 km
Hadley 3 Solar (South)3 MW5.2 km
Hadley 3 Solar (North)5 MW5.2 km
UMass PV Lot 491 MW5.3 km