Leake County, Mississippi · EIA plant ID 65697 · Operator: Mississippi Power Co
SolarBatteriesSolar PhotovoltaicBA: SOCO
Nameplate3MWSummer 3 MW
Generators2in service
Net generation3GWh12 mo to Dec 2025
Capacity factor25%solar units, summer MW
Heat rate—thermal plants only
First online2023

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300400MWh202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202320242025202624.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20231.319.9%—
20243.627.1%—
20253.324.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1ABatteriesBA1.51.5Jul 2023Operating—coming soon
1BSolar PhotovoltaicPV1.51.5Jul 2023Operating—coming soon

Owner / operator

Operator: Mississippi Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Mississippi Power Co100.0%3 MW

Nearby plants

Within 80 km.
Pearl River Solar Park LLC175 MW26.1 km
Ragsdale Solar LLC100 MW52.2 km
Attala551 MW52.6 km
Ratcliffe840 MW65.3 km
Sylvarena141 MW66.6 km
Sweatt42 MW73.7 km