← Back to map

BBARWA

San Bernardino County, California · EIA plant ID 65617 · Operator: distributed solar development, llc
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate2MWSummer 2 MW
Generators2in service
Net generation3GWh12 mo to Dec 2025
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2021

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh2022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20212022202320242025202617.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202103.0%—
20223.227.9%—
20233.219.0%—
2024318.2%—
20252.917.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
3998GSolar PhotovoltaicPV1.21.2Dec 2021Operating—coming soon
P3998Solar PhotovoltaicPV0.70.7Dec 2021Operating—coming soon

Owner / operator

Operator: distributed solar development, llc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
distributed solar development, llc100.0%2 MW

Nearby plants

Within 80 km.
Bear Valley Solar Plant—2 km
Bear Valley Battery Plant—4.5 km
Bear Valley Power Plant8 MW8.2 km
Lone Valley Solar Park I LLC10 MW15.2 km
Lone Valley Solar Park II LLC20 MW16.2 km
Santa Ana 13 MW26.2 km