← Back to map

Laredo Detention Facility - Solar 2, 3

Kern County, California · EIA plant ID 65464 · Operator: county of kern
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate5MWSummer 5 MW
Generators2in service
Net generation2GWh12 mo to Dec 2025
Capacity factor5%solar units, summer MW
Heat rate—thermal plants only
First online2021

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
012GWh2022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2021202220232024202520264.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20214.357.6%—
20227.316.3%—
20239.220.5%—
20245.111.4%—
202524.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
LDF2Solar PhotovoltaicPV3.13Nov 2021Operating—coming soon
LDF3Solar PhotovoltaicPV2.12.1Nov 2021Operating—coming soon

Owner / operator

Operator: county of kern. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
county of kern100.0%5 MW

Nearby plants

Within 80 km.
Lerdo East2 MW1.7 km
Sun Pacific - Lerdo3 MW3.4 km
Lerdo Middle—4.7 km
E&B Resources1 MW5.2 km
Imperator Solar—5.4 km
Double C Generation Limited Partnership50 MW5.9 km