Homestead Energy Storage LLCUnder construction

Los Angeles County, California · EIA plant ID 65398 · Operator: homestead energy storage, llc
BatteryCAISOBA: CISO

14 MW under construction (Batteries), first expected Oct 2027 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 14 MW building
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
HMSD1BatteriesBA1414planned Oct 2027Under construction—coming soon

Owner / operator

Operator: homestead energy storage, llc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Foothill Feeder9 MW2.9 km
Ameresco Chiquita Canyon9 MW6.8 km
Six Flags Magic Mountain—7 km
San Francisquito 246 MW9.8 km
Castaic1,682 MW11.5 km
Castaic Lake Phase II5 MW11.5 km